The Captain Field, operated by Texaco North Sea UK, is located 90 miles (145 kilometers) northeast of Aberdeen on Block 13/22a of the UK Continental Shelf. Texaco was 100% owner and operator, until Korea Captain Company Limited and Hanwha Energy acquired a shared 15% interest.
Captain was discovered in 1977 but wasn’t developed until 1995, when it was divided into three phases – A, B and C. The first phase of development came online in 1997, and it produces a heavy, sticky crude oil along with natural gas. The project cost a total of $800 million.
Field Development
The field development consisted of two platforms, a Bridge-Linked Platform, a Wellhead Protection Platform, and the Captain Floating Production Storage and Offloading ...
The Captain Field, operated by Texaco North Sea UK, is located 90 miles (145 kilometers) northeast of Aberdeen on Block 13/22a of the UK Continental Shelf. Texaco was 100% owner and operator, until Korea Captain Company Limited and Hanwha Energy acquired a shared 15% interest.
Captain was discovered in 1977 but wasn’t developed until 1995, when it was divided into three phases – A, B and C. The first phase of development came online in 1997, and it produces a heavy, sticky crude oil along with natural gas. The project cost a total of $800 million.
Field Development
The field development consisted of two platforms, a Bridge-Linked Platform, a Wellhead Protection Platform, and the Captain Floating Production Storage and Offloading vessel.
The field was drilled and developed by the well-head protection platform, which was part of the Captain A project, and from the field's subsea manifold, which was part of the Captain B project. Production from both is sent to the Captain FPSO, which provides treated water to re-inject for aquifer support.
Captain C project consisted of drilling two additional subsea wells tied-back to the platform via one production flowline. Development drilling of this phase commenced in December 2005, and it was performed by the Wellhead Protection Platform.
Bridge-Linked Platform/Wellhead Protection Platform
The jacket of the Bridge-linked platform is a four-legged vertical steel tower that was installed by Hereema’s heavy lift crane vessel, Thialf. The jacket is anchored to the seafloor by four 1,600-ton piles and serves as the base of the platform.
The drilling program consisted of 14 long-reach horizontal wells, employing innovative drilling and completion technology along with the first commercial deployment of gas-handling hydraulic submersible pumps, specially developed to handle the high gas content of the Captain B reservoir. The field also has features that enhance environmental performance, including waste heat recovery and gas export. Captain B was developed by a single 18-slot manifold connected via a suite of pipelines to a new process/utility platform.
The Captain Expansion Project facilities include a 5,500-ton topside deck and a 75-meter bridge, which links the Bridge Linked Platform (BLP) to the Wellhead Protector Platform. The facility was constructed by Kvaerner Oil & Gas Ltd. Completion of the project brought on stream an estimated 85,000 barrels of oil per day with a peak processing capacity of 100,000 bopd.
The subsea drilling and production center, in the eastern part of the field, contains crude oil and gas processing facilities and is linked to a suite of pipelines and an FPSO where crude oil is processed and stored. A shuttle tanker exports oil to Nigg Bay terminal, located in Cromarty Firth.
Production The Captain field came online March 6, 1997, and reached 63,000 bopd mid-year. The initial phase was followed by two more phases, with each one increasing the field's daily production level.
Production from Captain B commenced December 27, 2000 and produced 60,000 bopd with a plateau rate of 85,000 bopd during 2001.
Production from Captain C commenced July 4, 2006, and produced 9,000 bopd, with peak production reaching 15,000 bopd.
|
|
|
Wood Group to Service Chevron Facilities in the North Sea
Type: Contract Award
Feb. 2010 - Wood Group received a three-year operations and maintenance support services contract from Chevron North Sea Limited for its Alba, Captain and Erskine fields. Facilities included in the service arrangement include the Alba Northern Platform, the Captain FPSO and the Wellhead Production Platform, and the unmanned Erskine Platform, all located in the UK sector of the North Sea. The contract went into effect February 8, and includes two, one-year extension options exercisable by Chevron.
|
|
|
|
Chevron Selects Wood Group for North Sea Engineering Services
Type: Contract Award
Oct. 2009 - Wood Group was awarded a three-year engineering and construction contract by Chevron North Sea Limited for its Alba, Captain and Erskine fields. Worth an estimated £45 million over the initial three years, the contract is effective from October 1, 2009, and includes two, one-year extension options exercisable by Chevron. The contract covers the engineering and construction support services for the Alba Northern Platform, the Captain FPSO & Wellhead Production Platform and the unmanned Erskine Platform.
|
|
|
Captain FPSO
|
|
|
|
|
Under Construction - 1995 to 1996
|
|
|
Captain
|
|
Producing - Apr 06, 1997 to -
|
|
Under Development - 1995 to 1996
|
|
Exploratory Drilling - Apr 29, 1977 to May 18, 1977
Original discovery made on 13/22-1
|
|
|
|
The SubseaIQ Team works everyday to provide you with the latest information on the offshore field development market.
The following table provides you with a detailed record of each addition and update made to this project by the SubseaIQ team.
|
| UPDATE TYPE |
DATE |
DAYS AGO |
| Project Description Updated |
Aug 12, 2010 |
1011 |
|
| Field Updated |
Feb 18, 2010 |
1186 |
|
| Activity Added |
Feb 18, 2010 |
1186 |
|
| Activity Added |
Oct 06, 2009 |
1321 |
|
| Facility Updated |
Feb 11, 2009 |
1558 |
|
| Field Updated |
Feb 10, 2009 |
1559 |
|
| Project Description Added |
Nov 24, 2008 |
1637 |
|
| Field Added |
Jul 25, 2008 |
1759 |
|
| Facility Added |
Jul 25, 2008 |
1759 |
|
| Facility Status Added |
Jul 25, 2008 |
1759 |
|
| Field Status Added |
Jul 25, 2008 |
1759 |
|
Project Update History Search - View all the lastest updates made by the SubseaIQ team.
|
|
| Facility Name |
Captain FPSO |
|
| Duty |
Oil |
|
| Operator |
Chevron |
|
| Current Status |
Producing since 1997 |
|
| Host Type |
FPSO |
|
| Water Depth |
106 m / 350 ft |
|
| Dev.Cost |
$500,000,000 |
| |
| Region |
UK |
| |
| Location |
13/22a |
| Field Name |
Captain |
|
| Discovery Date |
May 1977 |
|
| Block |
13/22a |
|
| Reserve Type |
Oil |
|
| Current Status |
Producing |
|
| Production Start |
Apr 1997 |
|
| Water Depth |