| Operator: | Pemex (NOC) |
| Water Depth: | 100 m / 330 ft |
| Region: | N. America - Mexico |
| Country: | Mexico |
| Last Updated: | Jun 7, 2012 (view update history) |
|
What once was the second-largest crude oil producer for Mexico recently became the largest oil-producing field for the country. Ku-Maloob-Zaap is located 65 miles (105 kilometers) northwest of Ciudad del Carmen in the Gulf of Campeche. Situated in 328 feet (100 meters) of water, the project is made up of five fields, including Ku, Maloob, Zaap, Bacab and Lum.
The Ha-1A exploration well discovered the first field, Ku, in 1980. Next, the Maloob field was discovered in 1984, and the Zaap field was encountered in 1991. First production at Ku-Maloob-Zaap commenced from the Ku field in 1981, and projects have been ongoing to continually increase production from the complex.
Redevelopment
In December 2002, Pemex announced a US $3.15 million ...
What once was the second-largest crude oil producer for Mexico recently became the largest oil-producing field for the country. Ku-Maloob-Zaap is located 65 miles (105 kilometers) northwest of Ciudad del Carmen in the Gulf of Campeche. Situated in 328 feet (100 meters) of water, the project is made up of five fields, including Ku, Maloob, Zaap, Bacab and Lum.
The Ha-1A exploration well discovered the first field, Ku, in 1980. Next, the Maloob field was discovered in 1984, and the Zaap field was encountered in 1991. First production at Ku-Maloob-Zaap commenced from the Ku field in 1981, and projects have been ongoing to continually increase production from the complex.
Redevelopment
In December 2002, Pemex announced a US $3.15 million (42.2 million peso) investment in Ku-Maloob-Zaap to increase production over an eight-year period. The revitalization program included drilling 82 wells, 78 of which were development wells and four were nitrogen-injection wells, as well as installing 17 new platforms and constructing 32 new pipelines.
The new platforms will consist of seven drilling platforms, four production platforms, one production hub and compression center, four accommodation platforms and one platform that will host telecommunications.
In June 2004, ICA Fluor, a JV between Fluor and Empresas ICA Sociedad Controladora, was awarded a $169 million contract to engineer, procure, fabricate, transport and install four offshore drilling platforms on Ku-Maloob-Zaap. Weighing in at 30,000 tons (27,215 tonnes), the platforms were completed in August 2005.
In November 2004, Gulf Island Fabrication was awarded a contract to fabricate two jackets and piles for the HA-KU-S and HA-KU-M platforms that were installed on the Ku-Maloob-Zaap field in the first quarter of 2006.
Pemex installed Mexico's largest offshore platform at Ku-Maloob-Zaap in December 2006. Mexican company Swecomex built the 10,000-ton (9,072-tonne) KU-S platform, which has a production capacity of 250,000 bopd.
Furthermore, J. Ray McDermott was contracted to provide the Maloob-C drilling platform for the redevelopment project. Built at the company’s Altamira facility, the drilling platform is host 18 wells and consists of an eight-legged jacket and a two-level deck.
The new pipelines include five oil and gas pipelines extending 103 miles (166 kilometers) long, 20 gas lines, three nitrogen lines and four oil pipelines.
In a $46 million contract, Global Industries was awarded the installation work for two pipelines on Ku-Maloob-Zaap. One pipeline will link two platforms within the project facilities, and the other pipeline will connect a subsea installation with another platform on the project.
In 2007, Pemex drilled 12 new development wells at Ku-Maloob-Zaap and began injecting nitrogen into the reservoir to increase pressure and boost production from the formation.
In September 2009, Pemex awarded Demar Instaladora y Constructora a $120 million contract to fabricate a power station and install underwater cables to increase electricity supplies to Ku-Maloob-Zaap. The new power station will supply power to seven drilling platforms on the complex.
Yuum K'ak'naab FPSO
In 2005, Pemex announced its intent to hire an FPSO for the Ku-Maloob-Zaap field that would be able to process and offload both oil and gas. Named Yuum K'ak'naab, the FPSO was the first FPSO to be stationed in the Gulf of Mexico and is serving as a production hub and export terminal for the area. Contracted in a 15-year agreement with Pemex, the vessel is valued at $758 million and owned and operated by Bergesen Offshore.
DNV partnered with the Bergesen Group to convert the 360,000 dwt tanker Berge Enterprise at the Sembawang Shipyard in Singapore. The conversion work included coating of slop and ballast tanks, equipment installation, a modified cargo system, submerged pumps in the tanks, a new ringmain fire water system and upgraded living quarters for a crew of up to 110 people.
The vessel has a 600,000 bopd handling capability and 200,000 bopd processing capability, as well as gas export abilities. Boasting the third-largest oil production capability of other all FPSOs at the time, the Yuum K'ak'naab FPSO has the largest oil throughput of any FPSO in the world.
In May 2006, Aker Marine Contractors was awarded the contract to install the mooring and riser system for the Yuum K'ak'naab FPSO.
Arriving from Singapore in the Gulf of Mexico in March 2007, the FPSO is anchored northwest of the Ku-Maloob-Zaap field in waters measuring 328 feet (100 meters) deep. Yuum K'ak'naab began production on June 18, 2007.
Production
After initially commencing production in 1981, the Ku-Maloob-Zaap project has considerably ramped up output over the years. Ku-Maloob-Zaap produced an average of 740,000 bopd in 2008. In fact, the field surpassed the mega-producer Cantarell, also in the Gulf of Campeche, in July 2009 to become Mexico’s biggest producer, reaching an average of 797,000 bopd.
In an effort to proactively combat water seepage into the production, a problem that has greatly diminished production at Cantarell nearby, Pemex has already established water-separation facilities at Ku-Maloob-Zaap. Additionally, the company started injecting nitrogen into the reservoir early on and has been drilling more complex horizontal wells at Ku-Maloob-Zaap in an effort to sustain high levels of production. Pemex hopes to reach a production peak of 830,000 bopd at Ku-Maloob-Zaap and then maintain that level for the next seven years.
|
|
|
Fluor to Build Ku-Maloob-Zaap Production Platform
Type: Facility Construction
Jun. 2012 - ICA Fluor and Fluor Corporation have signed a contract with Pemex for the construction of an offshore production platform at the Ku-Maloob-Zaap field in the Gulf of Mexico. The contract has a value of $95 million. ICA Fluor and its subsidiary Industria del Hierro will be responsible for the procurement, construction, testing, and load-out of the Ayatsil-C platform. Weighing 11,832 tons and reaching 433 feet (132 meters) deep, Ayatsil-C is the first structure of this size to be installed by Pemex. The project is expected to be completed by the end of 2013.
|
|
|
|
Dragados to Transport, Install Platforms in Bay of Campeche
Type: Contract Award
Apr. 2010 - Dragados Offshore SA/Dragados Offshore Mexico SA de CV awarded two contracts to Saipem America. The first contract calls for transportation and installation of the PEMEX Litoral Tabasco Quarters Platform HA-LT-01, located in the Bay of Campeche offshore Mexico. The platform will be installed in late 2010 or early 2011 in 85 feet (26 meters) of water. The second contract awarded is for the transportation and installation of PEMEX Power Generation Platform PG-ZAAP-C, situated in 262 feet (80 meters) of water in the Bay. The platform will be installed in 2011 on the ZAAP field for the Ku-Maloob-Zaap project. The scope of work for both awards comprises transportation and installation of the jackets, fully integrated single-piece topsides weighing nearly 4,500 tons, and one bridge per platform connecting to existing facilities. Work also includes the engineering, procurement and project management.
|
|
|
|
Cameron to Supply Pumping Systems for KuMaloobZaap Platforms
Type: Contract Award
Oct. 2009 - Cameron's Process Systems group has received an order valued at $86 million for 16 multiphase pumping systems to be installed on three offshore platforms in the Ku-Maloob-Zaap field in the Gulf of Mexico. This represents the largest single order ever booked in Cameron's Process Systems business. Cameron will provide design engineering and packaging for the systems, which will include pumps, electric motors, piping, valves and control systems. The multiphase pumps will be provided by Leistritz Corporation, a longtime partner in subsea applications with Cameron's Subsea Systems group, and will be manufactured in Germany.
|
|
|
|
Pemex to Increase Power Supply to Ku-Maloob-Zaap
Type: Development Activity
Mar. 2009 - Pemex will increase power to the Ku-Maloob-Zaap oil field, located in the Bay of Campeche, Gulf Of Mexico, to optimize output at Mexico's largest producer. The company will install an underwater power cable and build an offshore platform to increase electricity supplies to Ku-Maloob-Zaap's production platforms.
|
|
|
|
Global Industries Awarded Pemex Pipeline Contract for KMZ
Type: Pipeline Construction
Oct. 2008 - Global Industries has been awarded a pipeline project from Pemex for pipeline work in the Ku-Maloob-Zaap field in the Bay of Campeche.
|
|
|
|
J. Ray Awarded Pemex Construction Contract
Type: Facility Construction
Dec. 2007 - J. Ray McDermott has been awarded a contract by Pemex for the fabrication of the Maloob-C Drilling Platform for the Ku-Maloob-Zaap complex.
|
|
|
|
DNV to Class First FPSO in the Gulf of Mexico
Type: Facility Construction
May. 2006 - The 360,000 dwt tanker Berge Enterprise is at the moment being converted in Singapore and is scheduled to start production at the Ku-Maloob-Zaap field offshore Mexico in the first quarter of 2007. Classed by DNV, the FPSO will be the first in the GOM and one of the largest globally.
|
|
|
Yuum K'ak'naab FPSO
|
|
Producing - Jun 18, 2007 to -
Arriving from Singapore in the Gulf of Mexico in March 2007, the FPSO is anchored northwest of the Ku-Maloob-Zaap field in waters measuring 328 feet (100 meters) deep. Yuum K'ak'naab began production on June 18, 2007.
|
|
Under Construction - Dec 27, 2005 to Jun 17, 2007
In 2005, Pemex announced its intent to hire an FPSO for the Ku-Maloob-Zaap field that would be able to process and offload both oil and gas. Named Yuum K'ak'naab, the FPSO was the first FPSO to be stationed in the Gulf of Mexico and is serving as a production hub and export terminal for the area. Contracted in a 15-year agreement with Pemex, the vessel is valued at $758 million and owned and operated by Bergesen Offshore.
|
|
|
Bacab
|
|
Producing - Under Dev. - Dec 2002 to -
Pemex began a redevelopment program on Ku-Maloob-Zaap in December 2002 that included adding 17 new platforms and 32 new pipelines, as well as drilling 82 new wells on the complex. For an investment of $3.15 million, the project is expected to span seven years. Additionally, an FPSO, the Yuum K'ak'naab, was brought onstream in 2007.
|
|
|
KMZ Platforms
|
|
Producing - Under Const. - Dec 2002 to -
In December 2002, Pemex announced a US $3.15 million investment in Ku-Maloob-Zaap to increase production over an eight-year period. The revitalization program included drilling 82 wells, 78 of which were development wells and four were nitrogen-injection wells, as well as installing 17 new platforms and constructing 32 new pipelines.
|
|
|
Lum
|
|
Producing - Under Dev. - Dec 2002 to -
Pemex began a redevelopment program on Ku-Maloob-Zaap in December 2002 that included adding 17 new platforms and 32 new pipelines, as well as drilling 82 new wells on the complex. For an investment of $3.15 million, the project is expected to span seven years. Additionally, an FPSO, the Yuum K'ak'naab, was brought onstream in 2007.
|
|
|
Zaap
|
|
Producing - Under Dev. - Dec 2002 to -
Pemex began a redevelopment program on Ku-Maloob-Zaap in December 2002 that included adding 17 new platforms and 32 new pipelines, as well as drilling 82 new wells on the complex. For an investment of $3.15 million, the project is expected to span seven years. Additionally, an FPSO, the Yuum K'ak'naab, was brought onstream in 2007.
|
|
Discovery (Drilled) - 1991 to 1991
The third field in the Ku-Maloob-Zaap project, Zaap was discovered in 1991.
|
|
|
Maloob
|
|
|
|
|
Producing - Under Dev. - Dec 2002 to Dec 2009
Pemex began a redevelopment program on Ku-Maloob-Zaap in December 2002 that included adding 17 new platforms and 32 new pipelines, as well as drilling 82 new wells on the complex. For an investment of $3.15 million, the project is expected to span seven years. Additionally, an FPSO, the Yuum K'ak'naab, was brought onstream in 2007.
|
|
Discovery (Drilled) - 1984 to 1984
The second field to be added to the Ku-Maloob-Zaap project, the Maloob oil field was discovered in 1984.
|
|
|
Ku
|
|
Producing - Under Dev. - Dec 2002 to -
Pemex began a redevelopment program on Ku-Maloob-Zaap in December 2002 that included adding 17 new platforms and 32 new pipelines, as well as drilling 82 new wells on the complex. For an investment of $3.15 million, the project is expected to span seven years. Additionally, an FPSO, the Yuum K'ak'naab, was brought onstream in 2007.
|
|
Producing - 1981 to Nov 2002
A year after discovery, first oil was produced from the Ku field. The project, which includes the Ku, Maloob, Zaap, Bacab and Lum fields has been under continual development to increase production.
|
|
Discovery (Drilled) - 1980 to 1980
The first of the five fields that would eventually make up the massive Ku-Maloob-Zaap project in the Mexican waters of the GOM, Ku was discovered in 1980.
|
|
|
|
The SubseaIQ Team works everyday to provide you with the latest information on the offshore field development market.
The following table provides you with a detailed record of each addition and update made to this project by the SubseaIQ team.
|
| UPDATE TYPE |
DATE |
DAYS AGO |
| Field Updated |
Jun 07, 2012 |
377 |
|
| Activity Added |
Jun 07, 2012 |
377 |
|
| Field Status Updated |
Apr 19, 2012 |
426 |
|
| Field Status Added |
Apr 19, 2012 |
426 |
|
| Field Updated |
Sep 01, 2011 |
657 |
|
| Project Description Updated |
Jun 23, 2011 |
727 |
|
| Project Description Updated |
May 05, 2011 |
776 |
|
| Project Description Updated |
Feb 17, 2011 |
853 |
|
| Project Description Updated |
Nov 24, 2010 |
938 |
|
| Activity Added |
Apr 07, 2010 |
1169 |
|
| Project Description Updated |
Oct 26, 2009 |
1332 |
|
| Field Updated |
Oct 21, 2009 |
1337 |
|
| Activity Added |
Oct 21, 2009 |
1337 |
|
| Project Description Updated |
Oct 12, 2009 |
1346 |
|
| Project Description Added |
Sep 10, 2009 |
1378 |
|
| Field Status Updated |
Sep 10, 2009 |
1378 |
|
| Field Added |
Sep 10, 2009 |
1378 |
|
| Field Status Added |
Sep 10, 2009 |
1378 |
|
| Field Updated |
Sep 10, 2009 |
1378 |
|
| Facility Status Added |
Sep 10, 2009 |
1378 |
|
| Facility Added |
Sep 10, 2009 |
1378 |
|
| Facility Updated |
Sep 10, 2009 |
1378 |
|
| Field Updated |
Apr 13, 2009 |
1528 |
|
| Field Status Added |
Apr 13, 2009 |
1528 |
|
| Field Added |
Mar 19, 2009 |
1553 |
|
| Activity Added |
Mar 17, 2009 |
1555 |
|
| Activity Added |
Oct 15, 2008 |
1708 |
|
| Activity Added |
Dec 14, 2007 |
2014 |
|
| Activity Added |
May 03, 2006 |
2604 |
|
Project Update History Search - View all the lastest updates made by the SubseaIQ team.
|
|
| Facility Name |
KMZ Platforms |
|
| Duty |
Oil |
|
| Operator |
Pemex (NOC) |
|
| Current Status |
Producing - Under Const. since 2002 |
|
| Host Type |
Fixed Platform |
|
| Water Depth |
100 m / 330 ft |
|
| Dev.Cost |
n/a |
| |
| Region |
Mexico |
| |
| Location |
|
| Facility Name |
Yuum K'ak'naab FPSO |
|
| Duty |
Oil/Gas |
|
| Operator |
Pemex (NOC) |
|
| Current Status |
Producing since 2007 |
|
| Host Type |
FPSO |
|
| Water Depth |
100 m / 330 ft |
|
| Dev.Cost |
$758,000,000 |
| |
| Region |
Mexico |
| |
| Location |
|
| Field Name |
Ku |
|
| Discovery Date |
Jan 1980 |
|
| Block |
|
|
| Reserve Type |
Oil |
|
| Current Status |
Producing - Under Dev. |
|
| Production Start |
Jan 1981 |
|
| Water Depth |
100 m / 330 ft |
| Field Name |
Maloob |
|
| Discovery Date |
Jan 1984 |
|
| Block |
|
|
| Reserve Type |
Oil |
|
| Current Status |
Producing |
|
| Production Start |
Jan 2010 |
|
| Water Depth |
100 m / 330 ft |
| Field Name |
Zaap |
|
| Discovery Date |
Jan 1991 |
|
| Block |
|
|
| Reserve Type |
Oil |
|
| Current Status |
Producing - Under Dev. |
|
| Production Start |
|
|
| Water Depth |
100 m / 330 ft |
| Field Name |
Bacab |
|
| Discovery Date |
|
|
| Block |
|
|
| Reserve Type |
Oil |
|
| Current Status |
Producing - Under Dev. |
|
| Production Start |
|
|
| Water Depth |
100 m / 330 ft |
| Field Name |
Lum |
|
| Discovery Date |
|
|
| Block |
|
|
| Reserve Type |
Oil |
|
| Current Status |
Producing - Under Dev. |
|
| Production Start |
|
|
| Water Depth |
100 m / 330 ft |
|