| |
| Aseng |
 |
| Operator: | Noble |
| Water Depth: | 945 m / 3,119 ft |
| Region: | Africa - West |
| Country: | Equatorial Guinea |
| Last Updated: | Nov 7, 2012 (view update history) |
|
The sanctioned Aseng field is located on Block I offshore Equatorial Guinea in a water depth of 3,100 feet (945 meters). Noble Energy serves as the operator and holds a 40% interest; Atlas Petroleum International Limited holds a 29% interest; Glencore Exploration EG Ltd holds a 25% interest; and PA Resources holds the remaining 6% interest.
In 2007, Aseng, formerly Benita, was discovered as a gas-condensate field and then confirmed by two appraisal wells. The first appraisal well identified the oil resources and the second well determined the down-dip reservoir limits.
Engineering and design work was conducted at Aseng while developmental contracts were secured. The Atwood Hunter semisub was leased to begin development work on the field, and arrived on location in ...
The sanctioned Aseng field is located on Block I offshore Equatorial Guinea in a water depth of 3,100 feet (945 meters). Noble Energy serves as the operator and holds a 40% interest; Atlas Petroleum International Limited holds a 29% interest; Glencore Exploration EG Ltd holds a 25% interest; and PA Resources holds the remaining 6% interest.
In 2007, Aseng, formerly Benita, was discovered as a gas-condensate field and then confirmed by two appraisal wells. The first appraisal well identified the oil resources and the second well determined the down-dip reservoir limits.
Engineering and design work was conducted at Aseng while developmental contracts were secured. The Atwood Hunter semisub was leased to begin development work on the field, and arrived on location in 2010.
Field Development
At a total cost of US $1.3 billion, Aseng was developed by five subsea wells tied to an FPSO. The oil is stored on the vessel unit, while the natural gas and water is re-injected into the reservoir to maintain pressure and maximize oil recoveries.
The leased Aseng FPSO is moored in 3,100 feet (945 meters) of water and has the design capabilities to handle 120,000 barrels of liquid per day, including 80,000 bopd. The vessel is also capable of re-injecting 170 MMcf/d (4 MMcm/d) into the reservoir for maximum recovery efforts.
Dresser-Rand received a contract from SBM Offshore to supply advanced turbomachinery for the Aseng FPSO. The company supplied gas compression and power generation packages for the FPSO. This contract was awarded in November 2009.
Technip received a contract for the development of the Aseng field. The contract included engineering, supply, installation and pre-commissioning of 19 miles (30 kilometers) of flexible pipe systems, including six flexible risers, and flexible flowlines and jumpers. Also included in the contract is the installation of the subsea production system, including manifolds, flying leads and umbilicals. Offshore installation was carried out mid-2011.
Aseng's production came online on Nov. 6, 2011 and is reaching a production level of 50,000 bopd. Over the life of the project, Noble expects to recover at least 100 to 120 million barrels of oil. An estimated 450 to 550 Bcf/d (1 Bcm/d) of gas resources will be produced as part of an integrated gas project once the pressure maintenance phase is completed.
The Alen project, formerly Belinda, is located in Block O, offshore Equatorial Guinea. Noble Energy operates the project, holding a 45% interest. Partners in the license include GEPetrol (30%), and Glencore Exploration (25%).
On Jan. 12, 2011, The Ministry of Mines, Industry, and Energy of the Republic of Equatorial Guinea approved Noble's Alen condensate/gas-recycling project.
Initial field development will include three production wells and three subsea natural gas injection wells tied to a processing platform. Produced condensate will be separated and piped to the Aseng FPSO on Block I, located about 15 miles (24 kilometers) to the south. Associated natural gas will be re-injected back into the reservoir to maintain pressure and maximize liquid recoveries.
The Alen processing facility, moored in 240 feet (73 meters) of water, is designed to handle 440 MMcf/d of natural gas and 40,000 bopd of condensate. The Alen field will commence production in 2013 and is anticipated to flow at a gross rate of 37,500 bopd. Natural gas re-injection is estimated at 380 MMcf/d during gas-recycling.
The total cost of the development is projected at US $1.6 billion.
|
|
|
Alen Development Remains On Schedule
Type: Development Activity
Nov. 2012 - PA Resources announced work on the Alen field development in Blocks O and I, offshore Equatorial Guinea, is progressing on schedule. The goal remains to achieve first production in the second half of 2013. Fabrication of platform facilities is in advanced stages and installation of flowlines and umbilicals is expected in 4Q 2012. The development will be comprised of a wellhead platform connected by a bridge to a central processing platform. Once on-line, Alen should produce 33,000 barrels of oil per day via three production wells.
|
|
|
|
Noble Energy Brings Aseng Online
Type: Production Start
Nov. 2011 - Noble Energy announced that first oil has flowed from the Aseng field into the FPSO on Nov. 6, 2011. Production has steadily ramped up to a rate of about 50,000 bopd as four subsea wells came online. The first tanker of oil from Aseng should be offloaded in December 2011. The operator is currently focusing on the Alen field development (that will connect to the Aseng FPSO), which should commence production in 2013. The Aseng field is located on Block I offshore Equatorial Guinea in a water depth of 3,100 feet (945 meters). Noble Energy operates the Aseng field with a 38 percent interest. Partners include Atlas Petroleum (27.55 percent), Glencore Exploration (23.75 percent), PA Resources (5.7 percent) and GEPetrol (5 percent).
|
|
|
|
Aseng to Commence Production by Year-End
Type: Status Update
Oct. 2011 - PA Resources, a partner in the Aseng field, says development of the field is ahead of schedule with production expected to commence by year-end. Development drilling is completed, and subsea installation activities are continuing. The Aseng field is located on Block I offshore Equatorial Guinea in a water depth of 3,100 feet (945 meters). Noble Energy serves as the operator and holds a 40 percent interest; Atlas Petroleum International Limited holds a 29 percent interest; Glencore Exploration EG Ltd holds a 25 percent interest; and PA Resources holds the remaining 6 percent interest.
|
|
|
|
Keppel On Track To Complete FPSO Aseng
Type: Status Update
Jul. 2011 - Keppel Shipyard's reconstruction of the Aseng FPSO is nearing completion. The company's work scope on FPSO Aseng includes refurbishment and life extension works, upgrading the accommodation facilities, installing and integrating the topsides, as well as fabricating and integrating the internal turret. The FPSO, chartered by Noble Energy for the development of the Aseng field in offshore Equatorial Guinea, is capable of processing 80,000 bopd and storing up to 1.7 MMbbl of oil. Aseng Production Company, a joint venture by SBM Offshore and Compania Nacional de Petroleo de Guinea Ecuatorial, the state oil company of Equatorial Guinea, will operate the FPSO. The Aseng field is located on Block I offshore Equatorial Guinea in a water depth of 3,100 feet (945 meters). Noble Energy serves as the operator and holds a 40% interest; Atlas Petroleum International Limited holds a 29% interest; Glencore Exploration EG Ltd holds a 25% interest; and PA Resources holds the remaining 6% interest.
|
|
|
|
McDermott Wins Fabrication of Alen Project Offshore West Africa
Type: Contract Award
Feb. 2011 - McDermott received a contract to fabricate a 15,000-ton platform for Noble Energy's Alen gas-condensate development project off the east coast of Bioko Island, Equatorial Guinea. The company will manage the construction, load out and installation aids for a 15,000-ton central production platform, including living quarters, and a smaller 2,000-ton wellhead jacket and pile, stated the press release. The project is expected to commence in the first quarter of 2011. The Alen project is located in Block O, offshore Equatorial Guinea. Noble Energy operates the project, holding a 45% interest.
|
|
|
|
Noble: Govt. Sanctions Offshore Equatorial Guinea Alen Project
Type: Status Update
Jan. 2011 - The Ministry of Mines, Industry, and Energy of the Republic of Equatorial Guinea has approved Noble's Alen condensate/gas-recycling project. The project was sanctioned by Noble in December 2010, followed by the approval of all partners. Initial field development will include three production wells and three subsea natural gas injection wells tied to a processing platform. Produced condensate will be separated and piped to the Aseng FPSO on Block I, located about 15 miles (24 kilometers) to the south. Associated natural gas will be re-injected back into the reservoir to maintain pressure and maximize liquid recoveries. The Alen processing facility, moored in 240 feet (73 meters) of water, is designed to handle 440 MMcf/d of natural gas and 40,000 bopd of condensate. The Alen field will commence production in 2013 and is anticipated to flow at a gross rate of 37,500 bopd. Natural gas re-injection is estimated at 380 MMcf/d during gas-recycling. The total cost of the development is projected to be US $1.6 billion. Currently, the front end engineering and design work was completed, and the operator is negotiating and awarding key project contracts, including the platform facility construction and installation, as well as necessary drilling resources. The Alen project is located in Block O, offshore Equatorial Guinea. Noble Energy operates the project, holding a 45% interest.
|
|
|
|
Mustang Receives FEED Contract for Belinda Project
Type: Contract Award
May. 2010 - Mustang, part of international energy services company John Wood Group PLC, will perform a front-end engineering design for the Belinda project in Block O, offshore Equatorial Guinea. The scope of the FEED includes the design of both the jacket and topsides of the facility, which will process gas condensate. The Belinda project is being designed as a gas cycling development designed to strip condensate from the field and re-inject the gas for future sales.
|
|
|
|
Development Work Continues on Aseng Field
Type: Status Update
Apr. 2010 - A total of five production wells, three injection wells and two gas injection wells are planned to be drilled in Block I on the Aseng field in 2010 and 2011. By summer, an additional drilling rig will arrive to assist in the development work. Production from the field is expected to commence in mid-2010. The recently sanctioned Aseng field is located on Block I offshore Equatorial Guinea in a water depth of 3,100 feet (945 meters). Noble Energy serves as the operator and holds a 40% interest; Atlas Petroleum International Limited holds a 29% interest; Glencore Exploration EG Ltd holds a 25% interest; and PA Resources holds the remaining 6% interest.
|
|
|
|
InterMoor Receives Preset Mooring Project for Aseng Field
Type: Contract Award
Apr. 2010 - InterMoor Inc. was awarded a contract to provide the design, engineering, procurement and installation services for preset moorings in the Aseng field. Five preset mooring legs will be installed at a water depth of roughly 3,445 feet (1,050 meters). Noble Energy will use the Pride South Pacific and the Atwood Hunter semisubs for the project, and the Maersk Terrier will be used as the installation vessel. The Aseng field is located on Block I offshore Equatorial Guinea in a water depth of 3,100 feet (945 meters). Noble Energy serves as the operator and holds a 40% interest; Atlas Petroleum International Limited holds a 29% interest; Glencore Exploration EG Ltd holds a 25% interest; and PA Resources holds the remaining 6% interest.
|
|
|
|
Noble Energy Awards Development Contract for Aseng Field
Type: Contract Award
Jan. 2010 - Technip received a contract for the development of the Aseng field. The contract includes engineering, supply, installation and pre-commissioning of 19 miles (30 kilometers) of flexible pipe systems, including six flexible risers, and flexible flowlines and jumpers. Also included in the contract is the installation of the subsea production system, including manifolds, flying leads and umbilicals. Offshore installation work should be carried out mid-2011. Aseng field is located on Block I offshore Equatorial Guinea in a water depth of 3,100 feet (945 meters). Noble Energy serves as the operator and holds a 40% interest; Atlas Petroleum International Limited holds a 29% interest; Glencore Exploration EG Ltd holds a 25% interest; and PA Resources holds the remaining 6% interest.
|
|
|
|
Dresser-Rand Supplies Equipment for Aseng FPSO
Type: Contract Award
Nov. 2009 - Dresser-Rand received a contract from SBM Offshore to supply advanced turbomachinery for an FPSO to be deployed in the Aseng field, which is located on Block I offshore Equatorial Guinea in a water depth of 3,100 feet (945 meters) and operated by Noble Energy. The company will supply gas compression and power generation packages for the FPSO, and the vessel will have the capacity to handle 120,000 barrels of liquid per day, including processing of 80,000 bopd, injection of up to 150,000 b/d of water, as well as handling 170 MMcf/d.
|
|
|
|
Noble Gets Go-Ahead for Aseng Oil Project in Equatorial Guinea
Type: Status Update
Jul. 2009 - Noble Energy announced that the Plan of Development for the Aseng oil project has been sanctioned by the Company, its partners, and the Ministry of Mines, Industry, and Energy of the Republic of Equatorial Guinea. Formerly known as Benita, Aseng was originally discovered in 2007 as a gas-condensate field in Block "I" offshore Equatorial Guinea. Initial development of the field will include five subsea wells flowing to an FPSO where the production stream will be separated.
|
|
|
Alen Platform
|
|
Under Construction - Feb 01, 2011 to -
|
|
|
Aseng FPSO
|
|
Producing - Nov 06, 2011 to -
|
|
Under Construction - Jul 22, 2009 to Nov 05, 2011
|
|
|
Alen (Belinda)
|
|
Under Development - May 04, 2010 to -
Mustang will perform a front-end engineering design for the Belinda project in Block O, offshore Equatorial Guinea.
|
|
Appraisal Drilling - Jun 2007 to Aug 2007
The O-3 appraisal well, located in 1,740 feet of water and approximately 4.2 miles southwest of the original Belinda discovery (O-1), was drilled to a total depth of 9,500 feet. The O-3 well successfully extended the Belinda discovery by establishing significant downdip resources.
|
|
|
Aseng
|
|
Producing - Nov 06, 2011 to -
|
|
Under Development - Jul 22, 2009 to Nov 05, 2011
Noble Energy announced that the Plan of Development for the Aseng oil project has been sanctioned by the Company, its partners, and the Ministry of Mines, Industry, and Energy of the Republic of Equatorial Guinea.
|
|
Discovery (Drilled) - Jan 2007 to 2007
Formerly known as Benita, Aseng was originally discovered in 2007 as a gas-condensate field in Block "I" offshore Equatorial Guinea.
|
|
|
|
The SubseaIQ Team works everyday to provide you with the latest information on the offshore field development market.
The following table provides you with a detailed record of each addition and update made to this project by the SubseaIQ team.
|
| UPDATE TYPE |
DATE |
DAYS AGO |
| Field Updated |
Nov 07, 2012 |
198 |
|
| Facility Updated |
Nov 07, 2012 |
198 |
|
| Activity Added |
Nov 07, 2012 |
198 |
|
| Facility Updated |
Dec 13, 2011 |
528 |
|
| Field Updated |
Nov 15, 2011 |
556 |
|
| Field Status Updated |
Nov 15, 2011 |
556 |
|
| Field Status Added |
Nov 15, 2011 |
556 |
|
| Facility Status Updated |
Nov 15, 2011 |
556 |
|
| Facility Status Added |
Nov 15, 2011 |
556 |
|
| Project Description Updated |
Nov 15, 2011 |
556 |
|
| Activity Added |
Nov 15, 2011 |
556 |
|
| Field Updated |
Oct 17, 2011 |
585 |
|
| Activity Added |
Oct 17, 2011 |
585 |
|
| Facility Added |
Sep 07, 2011 |
625 |
|
| Facility Status Added |
Sep 07, 2011 |
625 |
|
| Project Description Updated |
Sep 07, 2011 |
625 |
|
| Field Updated |
Jul 19, 2011 |
675 |
|
| Project Description Updated |
Jul 19, 2011 |
675 |
|
| Activity Added |
Jul 19, 2011 |
675 |
|
| Project Description Updated |
Jun 02, 2011 |
722 |
|
| Project Description Updated |
May 16, 2011 |
739 |
|
| Project Description Updated |
Feb 24, 2011 |
820 |
|
| Field Updated |
Feb 01, 2011 |
843 |
|
| Activity Added |
Feb 01, 2011 |
843 |
|
| Field Updated |
Jan 12, 2011 |
863 |
|
| Project Description Updated |
Jan 12, 2011 |
863 |
|
| Activity Added |
Jan 12, 2011 |
863 |
|
| Field Status Updated |
May 04, 2010 |
1116 |
|
| Field Updated |
May 04, 2010 |
1116 |
|
| Field Status Added |
May 04, 2010 |
1116 |
|
| Field Added |
May 04, 2010 |
1116 |
|
| Activity Added |
May 03, 2010 |
1117 |
|
| Field Updated |
Apr 28, 2010 |
1122 |
|
| Activity Added |
Apr 28, 2010 |
1122 |
|
| Field Updated |
Apr 13, 2010 |
1137 |
|
| Activity Added |
Apr 13, 2010 |
1137 |
|
| Project Description Updated |
Jan 20, 2010 |
1220 |
|
| Activity Added |
Jan 20, 2010 |
1220 |
|
| Field Updated |
Jan 20, 2010 |
1220 |
|
| Project Description Updated |
Jan 05, 2010 |
1235 |
|
| Field Updated |
Nov 16, 2009 |
1285 |
|
| Activity Added |
Nov 16, 2009 |
1285 |
|
| Field Updated |
Nov 02, 2009 |
1299 |
|
| Project Description Updated |
Jul 30, 2009 |
1394 |
|
| Field Added |
Jul 22, 2009 |
1402 |
|
| Field Status Added |
Jul 22, 2009 |
1402 |
|
| Field Status Updated |
Jul 22, 2009 |
1402 |
|
| Activity Added |
Jul 22, 2009 |
1402 |
|
| Project Description Added |
Jul 22, 2009 |
1402 |
|
| Field Updated |
Jul 22, 2009 |
1402 |
|
| Facility Added |
Jul 22, 2009 |
1402 |
|
| Facility Status Added |
Jul 22, 2009 |
1402 |
|
| Facility Updated |
Jul 22, 2009 |
1402 |
|
Project Update History Search - View all the lastest updates made by the SubseaIQ team.
|
|
| Facility Name |
Alen Platform |
|
| Duty |
Gas |
|
| Operator |
Noble Energy |
|
| Current Status |
Under Construction since 2011 |
|
| Host Type |
Fixed Platform |
|
| Water Depth |
530 m / 1,749 ft |
|
| Dev.Cost |
n/a |
| |
| Region |
Equatorial Guinea |
| |
| Location |
Block O |
| Facility Name |
Aseng FPSO |
|
| Duty |
Oil/Gas |
|
| Operator |
Noble Energy |
|
| Current Status |
Producing since 2011 |
|
| Host Type |
FPSO |
|
| Water Depth |
945 m / 3,119 ft |
|
| Dev.Cost |
n/a |
| |
| Region |
Equatorial Guinea |
| |
| Location |
Block I |
| Field Name |
Aseng |
|
| Discovery Date |
Jan 2007 |
|
| Block |
Block I |
|
| Reserve Type |
Oil/Gas |
|
| Current Status |
Producing |
|
| Production Start |
Nov 2011 |
|
| Water Depth |
945 m / 3,119 ft |
| Field Name |
Alen (Belinda) |
|
| Discovery Date |
|
|
| Block |
Block O |
|
| Reserve Type |
Gas |
|
| Current Status |
Under Development |
|
| Production Start |
|
|
| Water Depth |
530 m / 1,749 ft |
|