Gjoa Gjoa
PRODUCTION FACILITY
Facility Name Gjoa Semisub Duty Oil/Gas
Operator Statoil Current Status Producing since 2010
Host Type Semisub Water Depth 360 m / 1,188 ft
Dev.Cost $4,700,000,000 Region Norway
 
Location 35/9, 36/7
 
OIL & GAS FIELD
Field Name Gjoa Discovery Date May 1989
Block 35/9, 36/7 Reserve Type Oil/Gas
Current
Status
Producing Production Start Nov 2010
Water Depth 370 m / 1,221 ft



Field Name Vega Discovery Date May 1982
Block 35/11, 35/8,PL 248 Reserve Type Gas
Current
Status
Producing Production Start Dec 2010
Water Depth 380 m / 1,254 ft



Field Name Vega South Discovery Date Dec 1987
Block 35/11 Reserve Type Gas
Current
Status
Producing Production Start Dec 2010
Water Depth 380 m / 1,254 ft
 
 
Description
 
Discovered in 1989, Gjoa is located on Blocks 35/9 and 36/7 in the Norwegian North Sea, 28 miles (45 kilometers) offshore Norway in water depths of 1,181 feet (360 meters). The largest field development project on the North Sea's Norwegian Continental Shelf today, Gjoa is estimated to contain 82 million barrels of oil and condensate and 1.4 Tcf (40 Bcm) of gas.

Gjoa will be operated by two companies at different stages. Statoil is serving as the operator for the project through field development, and Gaz de France will be Gjoa's operator during the production phase of the field. Partners in the project include Gaz de France with a 30% interest, Petoro also with 30%, Statoil with 20%, Shell with 12% and RWE with the remaining 8%.

Field Development

Although the field was discovered 20 years ago, the plan for field development and operation wasn't agreed upon by licensees until 2006. Approved by the Norwegian Parliament in June 2007, Gjoa is the first development in the Sogn area, a new portion of the North Sea.

For a total investment of US $4.7 billion (NOK 29.3 billion), Gjoa is being developed by a semisubmersible production platform tied-back to five subsea templates. Field development plans for Gjoa include the satellite development of the Vega and Vega South fields nearby.

To reduce development costs, recovered hydrocarbons is transported through existing pipelines. Gas is transmitted via the British pipeline Flags to St. Fergus in Scotland. Oil is transported through a tie-in to the Troll II pipeline to the Mongstad refinery.

Semisubmersible Production Platform

There are three components related to construction and installation of the semisubmersible production platform. First, Aker Solutions was tapped in 2006 to fabricate and conjoin the topsides for the platform. The contract includes the detail engineering, procurement, construction and assembly of the topside and the connection with the platform hull.

Next, the partners awarded Leirvick Module Technology a $65 million (NOK 450 million) contract for the living quarters on the platform, comprising of a helideck, lifeboat station, living cabins and offices. Spanning nearly an acre, the 1,653-ton (1,500-tonne) living quarters will be able to accommodate 100 personnel.

In 2007, Samsung Heavy Industries was awarded the third supplier contract for the Gjoa platform. For a consideration of $150 million (NOK 900 million), Samsung is building the 15,432-ton (14,000-tonne) Gjoa platform hull. Assembly of the platform, including the hull, topsides and living quarters, will take place in Aker Stord, Norway.

Additionally, the Gjoa platform is the first floating platform to receive electricity from the mainland. A subsea cable, running from the Mongstad power plant north of Bergen, Norway, will supply the facility with electricity, reducing carbon dioxide emissions from the field.

Subsea Integration

The three-year, $427 million contract for the development drilling on Gjoa was awarded to Transocean Offshore in 2006. With a solid 13 wells on the schedule (nine oil wells and four gas wells), there are options for another three wells to be drilled during the contract. The Transocean Searcher semisub began Gjoa operations in January 2009.

Awarded in December 2006, FMC Technologies will provide 14 xmas trees and five subsea templates with manifolds for the development of Gjoa. The scope of the contract encompasses the production control systems, workover systems for well interventions and an umbilical option.

Italian Saipem was awarded the export pipeline installation contract in October 2007. Using the Castoro Sei pipe-laying vessel and starting in April 2009, Saipem installed a total of 115 miles (185 kilometers) of pipe from the Gjoa and Vega fields. A 28-inch-diameter gas pipeline will span 81 miles (130 kilometers) from Gjoa to the Flags pipeline. A 16-inch-diameter, 34-mile (55-kilometer) pipeline will connect Gjoa to the Troll II pipeline.

In December 2007, Danish NKT agreed to supply the engineering, procurement and fabrication of seven flexible risers for a consideration of $72 million (NOK 500 million). The 14- to 16-inch-diameter risers will measure between 2,264 and 2,395 feet (690 and 730 meters) long.

Technip is providing the fabrication and installation of subsea structures, as well as tie-in of the pipeline systems. In a $72 million (NOK 500 million) contract awarded in June 2008, Technip was chosen to perform fabrication and installation of tie-ins and expansion loops and guards, as well as the tie-in of risers, in-field and export pipelines. Technip will also perform water filling, cleaning, dimension control and pressure testing of pipelines. The Scandi Arctic vessel will perform structural installations, while the Normand Progress and Fugro Saltire will perform the pipeline tie-in and prep.

The five subsea templates were installed in October 2008, and development drilling commenced in November 2008. Tow out of the platform is expected to be in 2010 and production should commence from the field in September 2010.

Satellite Fields

Vega, located in the northern part of the North Sea, is located 50 miles (80 kilometers) west of Floro on Blocks 35/8 and 35/11.

Consisting of the Camilla, Belinda and Fram B discoveries in the early 1980s, the Vega field is in 1,247 feet (380 meters) of water. With a daily peak production rate of 247 MMcf (7 MMcm) of gas and 25,000 barrels of condensate, Vega boasts recoverable reserves of 636 Bcf (18 Bcm) of gas and 26 million barrels of condensate. The satellite field was developed via two subsea templates tied-back to the Gjoa semisubmersible platform, and production commenced on Dec. 2, 2010.

Discovered in 1987, Vega South is a gas and condensate field located in about 1,214 feet (370 meters) of water on Block 35/9. Another satellite field in the Gjoa field development plan, Vega South will be developed by a subsea template that will be connected to Vega and, ultimately, to the Gjoa platform. Production from Vega South commenced on Dec. 2, 2010.

Additionally, plans call for the eventual tie-in of the Aurora field.
 
Activities
 
Statoil Officially Opens Vega Field in North Sea
Date: Mar. 2011
Type: Operator Update
Statoil announced that the Vega field in the North Sea has officially opened. Production from the field commenced on Dec. 2, 2010. Gas and condensate flow from three subsea templates to the processing facility on the Gjoa platform, which is operated by GDF Suez. Following unitization of the two Vega licenses, Vega and Vega South, the partnership consists of Statoil (operator 54%), Petoro (24%), Bayerngas Norge (10%), Idemitsu Petroleum Norge (6%), and GDF Suez E&P (6%). The Vega and Vega Sor fields are located in PL 090C and 248 and lie in a water depth of 1,230 feet (375 meters).
Technip Receives EPIC Contract for Gjoa Development
Date: Mar. 2011
Type: Contract Award
GDF Suez awarded Technip an engineering, procurement, construction and installation contract for the Gjoa field development in the Norwegian sector of the North Sea. The contract includes engineering and fabrication work of two smoothbore gas export risers to connect the Gjoa platform with a gas export pipeline; removal of existing roughbore risers and installing two new smoothbore risers; and tie-in and pre-commissioning activities. Offshore installation is scheduled for completion in the second half of 2011. Gjoa is located on Blocks 35/9 and 36/7 in the Norwegian North Sea, 28 miles (45 kilometers) offshore Norway in water depths of 1,181 feet (360 meters).
RWE Dea Finds Oil in Titan Prospect, Near Gjoa Field
Date: Dec. 2010
Type: New Discovery
RWE Dea has discovered oil in the 35/9-6 S well on the Titan prospect in the Norwegian sector of the North Sea. The well proved petroleum over a gross column of more than 1,427 feet (435 meters) in the Viking group, as well as in the Brent and Dunlin groups. The reservoir rocks vary in reservoir quality and thickness, as well as different pressure regimes, and water contact was not encountered. Small-scale formation tests showed variable flow properties, and preliminary estimates place the size of the discovery between 12.5 and 62.8 million barrels of recoverable oil equivalent. To determine the exact size and extent of the discovery, the operator will have to appraise the find. The well was drilled by the Bredford Dolphin semisub in a water depth of 1,214 feet (370 meters). Situated about 9 miles (15 kilometers) west of the Gjoa field in the Norwegian North Sea, the well is the first to be drilled in this license. RWE Dea Norge AS is the operator of the license, with a 30% interest; Statoil owns 40%; and Idemitsu Petroleum Norge owns 30%.
Statoil Commences Production on the Vega Field
Date: Dec. 2010
Type: Production Start
Statoil has turned on the taps at its Vega gas and condensate field off Norway's west coast. The field was developed with three seabed templates sending gas and condensate to the Gjoa platform. It is estimated that the Vega field will deliver 7 million cubic meters of gas and 3,900 cubic meters of condensate daily. Vega consists of two licenses, Vega and Vega Sor, and initial startup of the field brings four wells online, with the final two expected to come online in April 2011. The Vega and Vega Sor fields are located in PL 090C and 248 and lie in a water depth of 1,230 feet (375 meters).
PSA Grants Consent for Gjoa's Transfer of Operatorship
Date: Nov. 2010
Type: Status Update
The Petroleum Safety Authority has granted consent for the transfer of operatorship of Gjoa from Statoil to GDF Suez. Statoil was the operator of the field during its development phase, and in accordance with a previously approved plan, the operator responsibility in the production phase is transferred to GDF Suez. Gjoa is located on Blocks 35/9 and 36/7 in the Norwegian North Sea, 28 miles (45 kilometers) offshore Norway in water depths of 1,181 feet (360 meters).
GDF Suez to Drill and Complete Production Wells on Gjoa
Date: Nov. 2010
Type: Drilling Operations
The Petroleum Safety Authority has granted GDF Suez consent to drill and complete wells on the Gjoa field using the Transocean Searcher semisub. The consent includes drilling and completing 11 wells, of which five were scheduled for completion before the start of production. The remaining wells are planned for completion by July 2012. Gjoa is located on Blocks 35/9 and 36/7 in the Norwegian North Sea, 28 miles (45 kilometers) offshore Norway in water depths of 1,181 feet (360 meters).
Statoil Commences Production at Gjoa
Date: Nov. 2010
Type: Production Start
Statoil announced the Gjoa oil and gas field commenced production on November 7. Oil and gas will produce from the field for at least 15 years, and Gjoa's facilities (with a design life of 30 years) will pave the way for further development in the area. The Gjoa platform is the first production facility to receive its power from land; electricity is transmitted through a 62-mile (100-kilometer) cable from Mongstad north of Bergen. It is estimated that Gjoa will produce roughly 17 MMcm/d. The field is located on Blocks 35/9 and 36/7 in the Norwegian North Sea, 28 miles (45 kilometers) offshore Norway in water depths of 1,181 feet (360 meters). Partners in the project include Gaz de France with a 30% operating interest, Petoro with 30%, Statoil with 20%, Shell with 12% and RWE with the remaining 8%.
Gassco Starts Up Gjoa Gas Pipeline
Date: Oct. 2010
Type: Pipeline Construction
Gassco, operator of the Gjoa Gas Pipe, announced that first gas flowed through the GGP pipeline on October 10. The 81-mile-long (130-kilometer-long), 28-inch-diameter line runs from Gjoa to the tie-in point on the Flags-pipeline, which will carry the gas to a receiving terminal at St. Fergus in Scotland. The pipeline will initially be used to import gas from Flags until the Gjoa platform becomes operational. It is estimated that Gjoa will produce roughly 17 MMcm/d. Gjoa is located on Blocks 35/9 and 36/7 in the Norwegian North Sea, 28 miles (45 kilometers) offshore Norway in water depths of 1,181 feet (360 meters).
Consent to Use Vega, Vega Sor on Gjoa
Date: Sep. 2010
Type: Subsea Equipment
Consent was given for the use of Vega and Vega Sor, which consist of three subsea templates located on Vega Nord, Vega Sentral and Vega Sor. These subsea templates will be tied to the Gjoa facility via a production pipeline and an umbilical. Gjoa is scheduled to commence production in October 2010. Gjoa is located on Blocks 35/9 and 36/7 in the Norwegian North Sea in a water depth of 1,181 feet (360 meters). Partners in the project include Gaz de France with a 30% interest, Petoro also with 30%, Statoil with 20%, Shell with 12% and RWE with the remaining 8%.
Statoil Turns on Gjoa's Power
Date: Jul. 2010
Type: Production Start
On July 11, Statoil turned on Gjoa's power, making it Norway's first floating platform to get its electrical power from the mainland. The electricity comes from Statoil's Mongstad facility, north of Bergen, through a 90,000-volt, 62-mile (100-kilometer) long subsea cable. The cable compromises both static and flexible parts, running from the seabed and up to the platform. Gjoa is located on Blocks 35/9 and 36/7 in the Norwegian North Sea in a water depth of 1,181 feet (360 meters). Partners in the project include Gaz de France with a 30% interest, Petoro also with 30%, Statoil with 20%, Shell with 12% and RWE with the remaining 8%.
Gjoa Platform Starts Journey to North Sea
Date: Jun. 2010
Type: Status Update
The Gjoa semisubmersible platform has left the Aker Solutions yard in Stord and is on its way to the North Sea where installation will take place. Aker Solutions designed, engineered and assembled the platform, which will connect to five subsea templates. The platform will have a topside weight of 24,251 tons (22,000 tonnes), and a hull dry weight of 16,535 tons (15,000 tonnes). The Gjoa deck measures 361 feet (110 meters) long and 279 feet (85 meters) wide, with a 469-feet (143-meter) long flare tower. Production from the field is scheduled for the fourth quarter of 2010. Gjoa is located on Blocks 35/9 and 36/7 in the Norwegian North Sea, 28 miles (45 kilometers) offshore Norway in water depths of 1,181 feet (360 meters). Two companies will operate Gjoa at different stages. Statoil is serving as the operator for the project through field development, and Gaz de France will be Gjoa's operator during the production phase.
Gjoa Platform Mated, Preparing for Production in 2010
Date: Dec. 2009
Type: Subsea Equipment
After its deck and hull were mated in Stord, Norway, the Gjoa platform was towed to the quay in order for the mechanical work of the facility to be carried out. The platform is expected to be ready for towing to the Gjoa field in April 2010. Located on Blocks 35/9 and 36/7 in the Norwegian North Sea in water depths of 1,181 feet (360 meters), Gjoa is estimated to contain 82 million barrels of oil and condensate and 1.4 Tcf (40 Bcm) of gas. After the field's development, Statoil will transfer operatorship to GDF Suez for the field's production phases. Partners in the project include Gaz de France with a 30% interest, Petoro also with 30%, StatoilHydro with 20%, Shell with 12% and RWE with the remaining 8%.
Gjoa Hull Makes Safe Voyage Through Gulf of Aden
Date: Sep. 2009
Type: Status Update
The hull of the North Sea Gjoa platform is on its way to Norway from the Samsung shipyard in South Korea. The development of Gjoa, Vega and Vega Sor, which is currently the biggest development project on the Norwegian Continental shelf, is opening up a new part of the North Sea for oil and gas production. Vega and Vega Sor will be developed using subsea installations connected to the Gjoa platform. After arrival, it will be moored until Christmas while awaiting assembly with the topsides.
Grenland Group Delivers Gjoa Subsea Structures
Date: Sep. 2009
Type: Subsea Equipment
Grenland Group delivered seven subsea structures to the Gjoa field. Technip will use the structures to tie-in the Gjoa platform with the subsea systems on the field. The US $6.6 million (NOK 40 million) Technip contract for the fabrication of structures for the Gjoa Structures, Tie-ins and RFO Project was awarded to Grenland Group last summer. The total weight of the structures was approximately 551 tons (500 tonnes) at delivery. Previously Grenland Group has delivered five large subsea structures with a total weight of more than 1,874 tons (1,700 tonnes) to FMC Technologies for StatoilHydro's Gjoa project. Gjoa is an oil and condensate field situated north of the Troll field -- about 40 miles (65 kilometers) southeast of Floro, Norway.
StatoilHydro to Recover Big Gains from Vega South
Date: Jul. 2009
Type: Development Activity
A few simple modifications to wells already planned will allow StatoilHydro to recover seven million barrels of oil and a billion standard cubic meters of associated gas from Vega South. Located in the northern North Sea, this structure forms part of a project which also embraces the Vega North and Vega Central discoveries. Plans call for these finds to be developed as a gas and condensate (light oil) field, but StatoilHydro will now also produce a thin layer of light crude from the southern discovery. Extra meters must be installed on the wellheads to permit recovery of the light crude. Plans call for Vega to come on stream through the Gjoa tie-in during the fourth quarter of 2010 at an estimated cost of US $1 Billion (NOK 7 Billion).
StatoilHydro Gets Go-Ahead to Use Bideford Dolphin in North Sea
Date: Jun. 2009
Type: Development Activity
StatoilHydro was granted consent for the use of the Bideford Dolphin semisub to conduct production drilling, completion and well clean up on the Vega and Vega Sor fields. The fields are gas and condensate fields under PL 090C and 248, and are located in a water depth of 1,230 feet (375 meters). An overall Plan for Development and Operation (PDO) for the fields was approved by the authorities in June 2007. According to the plan, production will start in the autumn of 2010.
Subsea 7 Completes Dev't Project on Vega Fields in North Sea
Date: Apr. 2009
Type: Development Activity
Subsea 7 commenced the subsea work on the StatoilHydro-operated Vega and Vega South fields, located in the Norwegian North Sea in 1,247 feet (380 meters) of water. The EPCI workscope includes three rigid flowlines, totaling 32 miles (51 kilometers) in length, as well as three umbilicals and three MEG lines. Vega and Vega South are being developed as a subsea tie-back to the Gjoa facility, and production is expected in the fourth quarter of 2010.
StatoilHydro Kicks Off Drilling at Gjoa
Date: Jan. 2009
Type: Status Update
The Transocean Searcher drilling rig has started drilling the first of a total of 13 production wells on the Gjoa field in the North Sea. The rig will drill nine oil wells and four gas wells.
StatoilHydro Plans to Tie-In Vega Satellites to Gjoa
Date: Jan. 2009
Type: Development Activity
Activity on Vega and Vega South will be high in 2009. The subsea systems on both satellite fields will be tested early in the year. In the second quarter the subsea templates will be installed. At the same time pipes will be laid, structures will be installed and tie-ins will be carried out. When the subsea systems are ready, drilling can start as scheduled in July 2009.
Gaz de France Taps Comos for Gjoa Management Work
Date: Dec. 2008
Type: Operator Update
In 2010, Gaz de France Norge is set to become the operator on the Gjoa field, and the company has designated Cosmos to manage all operational engineering, documentation and maintenance management tasks.
StatoilHydro Completes Template Installation on Gjoa
Date: Oct. 2008
Type: Development Activity
StatoilHydro's head of marine operations says that Four integrated templates and a satellite structure have been installed on the seabed of the Gjoa field. The offshore operations have been conducted as planned. Production start is expected in the fall of 2010.
Transocean Taps Grenland Group for Work on Semsiub
Date: Sep. 2008
Type: Development Activity
Transocean has awarded Grenland Group an EPCI contract for modification of the skidding system of Transocean Searcher semisub. The rig will be operating for StatoilHydro at the Gjoa field. The contract comprises delivery of turn tables, skidding units, pulling tractor and associated equipment. The contract also includes structural reinforcements of the main deck.
Gjøa contract to Technip Norge 
Date: Jun. 2008
Type: Contract Award
StatoilHydro has awarded the contract for the fabrication and installation of structures and tie-in of the pipeline systems for the Gjøa project to Technip Norge AS.
StatoilHydro's Gjoa Project Meets Safety Requirements
Date: May. 2008
Type: Status Update
On April 30, 2008, the Petroleum Safety Authority Norway (PSA) conducted an audit of StatoilHydro's management of the Gjoa project in the well safety area. No non-conformities with the regulatory requirements were found.
Simtronics Receives Order for Expansion of GJOA Semi EPCH Project
Date: Feb. 2008
Type: Status Update
Simtronics ASA has today received a purchase order from Aker Kvaerner Stord AS for an expansion of the GJOA Semi EPCH project. The expansion order has a value of more than U.S. $427,000. The initial order for this project was announced on June 4, 2007. The total confirmed order for supply of a complete active fire fighting solution for the GJOA Semi EPCH project is now in excess of U.S. $6.9 million.
North Sea Gjoa Contract to IKM Gruppen
Date: Feb. 2008
Type: Contract Award
On behalf of the Gjoa license and the future operator, Gaz de France, StatoilHydro awarded the main operations support contract for the Gjoa platform in the North Sea to IKM Gruppen AS. "This was a much sought-after contract. After a pre-qualification round five bidders delivered very good bids," says Kjetel Digre, StatoilHydro's project manager for Gjoa.
Saipem Grabs Gjoa Contract
Date: Oct. 2007
Type: Pipeline Construction
Saipem UK has been awarded a contract for the installation of oil and gas export pipelines from the Gjoa field in the North Sea. StatoilHydro is the development operator for the field. Saipem will lay a total of 185 kilometers of pipeline for the transport of oil and gas from the Gjoa and Vega fields. The 28 inch gas pipeline will be around 130 kilmometers long, running from Gjoa to the UK Flags trunkline, which carries gas onwards to St Fergus in Scotland.
Gjoa Umbilicals Contract to Aker Kvaerner
Date: Sep. 2007
Type: Contract Award
Aker Kvaerner has signed a contract with Statoil for the manufacturing and supply of steel tube umbilical control cables for the Gjoa field in the North Sea. The contract is worth approximately NOK 260 million. Aker Kvaerner will deliver about 16 kilometers of dynamic and static umbilicals to Statoil. The umbilicals will be manufactured and delivered out of Aker Kvaerner Subsea's facility in Moss, Norway.
Gjoa Approved by Norwegian Parliament
Date: Jun. 2007
Type: Development Activity
The Gjoa field will be developed with a floating production platform with plans calling for it to come on stream in 2010. Gas will be sent via the UK Flags pipeline to St Fergus in Scotland. Oil will be piped to the Troll II line and further to the Statoil-operated Mongstad refinery north of Bergen.
ABB to Manufacture, Install Gjoa Power Cable
Date: May. 2007
Type: Status Update
Statoil has sent a letter of intent to Swedish company ABB Power Technologies for the manufacture and installation of a power cable from the North Sea's Gjoa field. Power cable laying will begin in 2009, with final tie-in to the field in 2010.
Norway to Make Final Decision on Gjoa by Summer
Date: May. 2007
Type: Development Activity
The Norwegian government has proposed that the North Sea's Gjoa field be developed in accordance with the plan for development and operation (PDO), at the Council of State today. The Norwegian parliament (Storting) will make a final decision before the summer.
Final Gjoa Platform Contract Ready
Date: Apr. 2007
Type: Contract Award
Samsung Heavy Industries has been given the assignment of building the Gjoa platform hull. The final key platform supplier is now in place. The construction contract has a value of US $150 million, or around NOK 900 million. Samsung has commenced mobilization activities with a planned fabrication start in South Korea in February 2008. Up to 1,000 people will be working on the 14,000-tonne hull structure.
Dresser-Rand to Supply Turbomachinery for Gjoa
Date: Mar. 2007
Type: Contract Award
Dresser-Rand Group Inc. will supply advanced turbomachinery for Statoil's semi-submersible production platforms to be located in the Gjoa field, approximately 50 kilometers off southwest Norway. The contract to provide compression equipment and drivers to Norway's state-owned oil and gas company is estimated at more than $50 million USD. The equipment will be used for recompression and export services at the new oil and gas field. Dresser-Rand booked the order in February 2007.
Statoil Awards Gjoa Quarters Job to Leirvik
Date: Feb. 2007
Type: Contract Award
Statoil has awarded a NOK 450-million contract to Leirvik Module Technology AS to build the living quarters for the Gjoa platform in the North Sea. Statoil is currently the operator of the project. Covering a unit complete with helideck and lifeboat station, this engineering, procurement and construction (EPC) job will be executed at Stord south of Bergen. The completed quarters module is to be installed on the platform at Aker Kvaerner's nearby yard in Stord, which is the assembly site for hull and topsides of the Gjoa floater.
Statoil Awards Drilling Contract for Gjoa
Date: Dec. 2006
Type: Contract Award
As development operator, Statoil has signed an agreement with Transocean for drilling of production wells at the North Sea's Gjoa field. Valid for three years, the contract is worth around US $427 million. The deal covers drilling of 13 wells, with options for a further three. The Transocean Searcher rig will drill the wells. First drilling is planned to start in October 2008.
FMC Technologies to Supply Subsea Systems for Gjoa
Date: Dec. 2006
Type: Subsea Equipment
FMC Technologies has signed a contract with Statoil to supply subsea systems for the Gjoa project, offshore Norway. The value of this contract is approximately $210 million in revenue. This contract covers the supply of 14 subsea trees, 5 template structures with manifolds, a topside control system and work-over systems. The subsea system will be engineered and manufactured at FMC Technologies' facility in Kongsberg, Norway. First deliveries are scheduled for July 2008.
Aker Kvaerner Wins Gjoa Topsides Work from Statoil
Date: Sep. 2006
Type: Contract Award
A letter of intent on fabricating and mating the topsides for the semi-submersible platform planned on Statoil's Gjoa field in the North Sea has been awarded to Aker Kvaerner. The two sides now aim to conclude a final contract covering detail engineering, procurement, construction and assembly of the topside plus its mating with the platform hull.
Statoil Reports Progress on Gjoa
Date: Aug. 2006
Type: Status Update
Statoil said that the licensees in the Gjoa license in the North Sea have decided to use a semi-submersible platform for the field development, targeting first oil and gas in 2010. The aim is to send the plan for development and operation (PDO) to the Ministry of Petroleum and Energy during the autumn. A final cost estimate will also be available by then.
Statoil Awards FEED Contract to Aker Kvaerner for Gjoa Platform
Date: Jan. 2006
Type: Contract Award
A front-end engineering design (Feed) contract has been awarded by Statoil to Aker Kvaerner Engineering & Technology for a production platform on the Gjoa field in the North Sea. Awarded on behalf of the Gjoa licensees, the contract is based on Statoil's recommended solution with a semisubmersible production platform tied back to subsea wells.
Operatorship of Gjoa Discovery to be Split
Date: Feb. 2004
Type: Operator Update
The partners in production license 153 have unanimously resolved that Gaz de France Norge (GdFN) and Statoil will split the operatorship for the Gjoa discovery in the North Sea. The former operator, Norsk Hydro, reached agreement with GdFN last autumn on transferring its 30 per cent holding in the find to the French company. The licence then recommended that Statoil serves as development operator for Gjoa, with GdFN taking over in the production phase. This model has now been approved by the authorities.
 
Status History
 
Gjoa Semisub

Producing - Nov 08, 2010 to -
Under Construction - Aug 2006 to Nov 07, 2010
The licensees agreed to a field development plan in August 2006, and the Norwegian parliament approved the PDO in June 2007. The installation of subsea equipment is complete, and drilling began in October 2008. Production is expected to commence in September 2010 on Gjoa and in October 2010 from the two satellite fields, Vega and Vega South.
Gjoa

Producing - Nov 07, 2010 to -
Under Development - Jul 11, 2010 to Nov 06, 2010
On July 11, Statoil turned on Gjoa's power, making it Norway's first floating platform to get its electricity from the mainland.
Under Development - Jun 14, 2007 to Jul 2010
Gas will be transported in the British pipeline Flags to St. Fergus in Scotland. Oil will be piped via a tie-in to the Troll II pipeline and further to the StatoilHydro-operated Mongstad refinery near Bergen. Start-up of oil and gas production is expected in 2010.
Discovery (Appraised) - Aug 14, 1998 to Jun 13, 2007
The well was permanently abandoned on 12 August 1998 as a dry well.
Appraisal Drilling - Jul 13, 1998 to Aug 13, 1998
Well 35/9-4 S was spudded with the semi-submersible installation Transocean Leader on 13 July 1998 and drilled to TD at 1261 m in the Paleocene Lista Formation. Well 35/9-4 SR was spudded immediately after.
Discovery (Appraised) - Apr 04, 1991 to Mar 31, 1996
Well 35/9-2 was permanently abandoned on 3 April 1991 as a gas/oil discovery.
Appraisal Drilling - Jan 01, 1991 to Apr 03, 1991
Wildcat/Appraisal well 35/9-2 was spudded with the semi-submersible installation Vildkat Explorer on 1 January 1991 and drilled to TD at 2885 m in Caledonian basement. Due to hole angle problems, the well had to be re-spudded twice before drilling proceeded.
Discovery (Drilled) - May 08, 1989 to Dec 31, 1990
Well 35/9-1 was prepared for testing. It was suspended as an oil and gas discovery on 7 May 1989. Well testing was postponed for a re-entry after the TOGI assignment.
Exploratory Drilling - Apr 01, 1989 to May 07, 1989
Well 35/9-1 was drilled on the M ål øy Slope north of the Horda Platform with Transocean's Polar Pioneer. The well was drilled to a total depth of 2350 m in crystalline basement rock.
Vega South

Producing - Dec 02, 2010 to -
Under Development - Jun 14, 2007 to Dec 01, 2010
Vega South will be developed by a subsea template that will be connected to Vega and, ultimately, to the Gjoa platform. Production from Vega South is expected to start in October 2010.
Discovery (Appraised) - Apr 21, 1992 to Jun 13, 2007
Wildcat well 35/11-6 was permanently abandoned on 20 April 1992. The well contained a limited accumulation of live oil. It is classified as well with shows.
Appraisal Drilling - Jan 30, 1992 to Apr 20, 1992
Wildcat well 35/11-6 was spudded with the semi-submersible installation Sovereign Explorer on 30 January 1992 and drilled to TD at 3990 m in the Early Jurassic Statfjord Formation.
Discovery (Drilled) - Dec 05, 1987 to Jan 29, 1992
Wildcat well 35/11-2 was plugged and abandoned on 4 December 1987 as a gas and condensate discovery.
Exploratory Drilling - Jul 20, 1987 to Dec 04, 1987
Wildcat well 35/11-2 was spudded with the semi-submersible rig Treasure Scout on 20 July 1987 and drilled to TD at 4025 m in Early Jurassic rocks.
Vega

Producing - Dec 02, 2010 to -
Under Development - Jun 14, 2007 to Dec 01, 2010
Field development plans for Vega include two subsea templates tied back to the Gjoa semisubmersible platform. The PDO was submitted to the authorities on Dec. 15, 2006. The start up of production at the Vega field is planned for October 2010.
Discovery (Drilled) - May 22, 1982 to Jun 13, 2007
Exploratory Drilling - Jul 27, 1980 to May 21, 1982
Two wildcat wells were drilled and both reported discoveries. Wells 35/8-1 and 35/8-2 were drilled by the Sedco 704 to a depth of over 4300 m.
 
Project Map Europe - North Sea
Line Separator
Project Image
Gjoa Field
 
Gjoa
 
Template Installation at Gjoa
 
Gjoa
 
Gjoa
 
Transocean Searcher
 
Transocean Searcher