Offshore Field Development Projects
Ofon Ofon
Operator:Total
Water Depth:40 m / 132 ft
Region:Africa - West
Country:Nigeria
Last Updated:Feb 27, 2013    (view update history)
Project Description
The Ofon field is located in OML 102 roughly 40 miles off the coast of Nigeria in waters 130 feet deep. Ofon containes proved and probably reserves of 350 MMboe. Production from the field began in 1997. Current production rates average 30,000 Bopd.

Phase 2 of the Ofon development began in 2012 with first oil expected by 2015. The additional reserves that should be realized upon completion of Phase 2 will increase output by 60,000 Bopd.

The development project consists of the installation of two production platforms, one processing platform and one living quarters platform. Phase 2 should be complete and online by 2015.
The Ofon field is located in OML 102 roughly 40 miles off the coast of Nigeria in waters 130 feet deep. Ofon containes proved and probably reserves of 350 MMboe. Production from the field began in 1997. Current production rates average 30,000 Bopd.

Phase 2 of the Ofon development began in 2012 with first oil expected by 2015. The additional reserves that should be realized upon completion of Phase 2 will increase output by 60,000 Bopd.

The development project consists of the installation of two production platforms, one processing platform and one living quarters platform. Phase 2 should be complete and online by 2015.
Activities
Status Updates
Total Starts Second Phase of Ofon Development in Nigeria
Type: Development Activity

Feb. 2012 - Total has commenced the second phase of the Ofon field development offshore Nigeria. Construction and installation contracts were awarded for Ofon Phase 2, which is scheduled to come on stream in 2014. The Ofon field is located in OML 102, 40 miles (65 kilometers) off the Nigerian shores in a water depth of 130 feet (40 meters). Total said that this phase of development will unlock the field's undeveloped reserves and increase production to 90,000 barrels of oil equivalent per day from 30,000 barrels, by installing four new platforms: two production platforms, a processing platform and an accommodation platform. Most of the development is dedicated to recovering natural gas, which will be compressed and evacuated to shore. The partners in OML 102 are Total (40 percent, operator) and Nigerian National Petroleum Corporation (60 percent).

Ofon 1
Under Construction - 2012 to -

Ofon 2
Under Construction - 2012 to -

Ofon
Producing - Under Dev. - 2012 to -

Producing - 1997 to 2011

Ofon AMD1
Producing - 1997 to -

Update History
The SubseaIQ Team works everyday to provide you with the latest information on the offshore field development market. The following table provides you with a detailed record of each addition and update made to this project by the SubseaIQ team.
UPDATE TYPE DATE DAYS AGO
Project Description Added Feb 27, 2013 417
Field Status Updated Feb 27, 2013 417
Field Status Added Feb 27, 2013 417
Field Updated Feb 27, 2013 417
Facility Added Feb 27, 2013 417
Facility Status Added Feb 27, 2013 417
Facility Updated Feb 27, 2013 417
Field Added Feb 07, 2012 803
Field Updated Feb 07, 2012 803
Field Status Added Feb 07, 2012 803
Activity Added Feb 07, 2012 803

    Project Update History Search - View all the lastest updates made by the SubseaIQ team.
 
 
 
 
Facility Name Ofon 2
Duty Oil/Gas
Operator Total
Current Status Under Construction since 2012
Host Type Fixed Platform
Water Depth 40 m / 132 ft
Dev.Cost n/a
 
Region Nigeria
 
Location OML 102
Facility Name Ofon AMD1
Duty Oil/Gas
Operator Total
Current Status Producing since 1997
Host Type Fixed Platform
Water Depth 40 m / 132 ft
Dev.Cost n/a
 
Region Nigeria
 
Location OML 102
 
Field Name Ofon
Discovery Date
Block Oil Mining Lease 102
Reserve Type Gas
Current Status Producing - Under Dev.
Production Start Jan 1997
Water Depth 40 m / 132 ft