Blind Faith Blind
Operator:Chevron
Water Depth:1,981 m / 6,537 ft
Region:N. America - US GOM
Country:US
Last Updated:Oct 5, 2009    (view update history)
Project Description
Discovered in 2001 by Chevron, Blind Faith is located on Mississippi Canyon Blocks 696 and 695 in the Gulf of Mexico. Chevron, the operator, holds a 62.5% interest, and Kerr-McGee holds a 37.5% interest.

In June 2001, the Blind Faith discovery well encountered more than 200 feet (61 meters) of net pay in Miocene sands at depths of 20,900 feet to 24,300 feet (6,370 to 7,407 meters). Following the discovery, an appraisal well was drilled in 2004, which confirmed the previous findings. The field has an estimated gross resource potential exceeding 100 Mmboe.

Field Development

The field is developed by the Blind Faith semisubmersible platform, 160 miles (257 kilometers) southeast of New Orleans, La. Moored in 6,500 feet (1,981 meters) of water ...
Discovered in 2001 by Chevron, Blind Faith is located on Mississippi Canyon Blocks 696 and 695 in the Gulf of Mexico. Chevron, the operator, holds a 62.5% interest, and Kerr-McGee holds a 37.5% interest.

In June 2001, the Blind Faith discovery well encountered more than 200 feet (61 meters) of net pay in Miocene sands at depths of 20,900 feet to 24,300 feet (6,370 to 7,407 meters). Following the discovery, an appraisal well was drilled in 2004, which confirmed the previous findings. The field has an estimated gross resource potential exceeding 100 Mmboe.

Field Development

The field is developed by the Blind Faith semisubmersible platform, 160 miles (257 kilometers) southeast of New Orleans, La. Moored in 6,500 feet (1,981 meters) of water with production wells in 7,000 feet (2,164 meters), Blind Faith's topsides weigh more than 7,000 tons (6,350 tonnes) with two production facilities and two main processing decks. The facility has a total displacement of more than 40,000 tons (36, 287 tonnes), with an overall height that is comparable to a 29-story building.

FMC Technologies Inc. received a $39 million contract to supply the subsea systems for Blind Faith, including three high-pressure, high-temperature subsea trees and associated structures, production control systems, and other related equipment.

Expro's Subsurface Systems business unit provided electro-hydraulic deepwater safety systems to support Blind Faith during its commercial life.

Subsea 7 installed flowlines, including the associated pipeline end terminations (PLETs) and pre-laid steel catenary risers (SCRs).

Aker Kvaerner delivered an advanced dynamic umbilical, including engineering and project management. Aker Kvaerner Subsea supplied 31,168 feet (9,500 meters) of dynamic steel tube umbilical, including all surface and subsea terminations that are installed in 6,890 feet (2,100 meters) of water.

Gulf Island Fabrication constructed the topsides for the Blind Faith platform.

Aker Kvaerner also received a contract to provide the engineering, procurement, construction, transportation and installation of the semi-submersible hull and mooring system with the chartered construction vessel BOA Sub C. This development utilized Aker Kvaerner's deep draft semi-submersible (DDS) concept, which was conceived specifically for the application of steel catenary risers in the ultra-deepwater and current-heavy Gulf of Mexico environment. The contract value of the hull and mooring system totaled US $120 million.

Production

Production of Blind Faith commenced Nov. 1, 2008. Daily production is expected to peak at 65,000 bopd and 55 MMcf/d (1.6 MMcm/d) for the next several months.

Activities
Status Updates
Chevron Expects to Ramp Up Production at Blind Faith in 1Q 2009
Type: Status Update

Jan. 2009 - Chevron reported in its 4Q 2008 Earnings Report that total production volumes at its Blind Faith project is expected to ramp up during the first quarter of 2009 to 65,000 barrels of crude oil and 55 million cubic feet of natural gas per day. Blind faith was the third major project completed in deepwater Gulf of Mexico in the second half of 2008.

Chevron's Blind Faith Starts Up Production in Deepwater GOM
Type: Production Start

Nov. 2008 - Chevron Corporation has started crude oil production from its Blind Faith Field in the deepwater Gulf of Mexico. First oil from Blind Faith was achieved on Nov. 11, 2008. Daily production is expected to ramp up to approximately 65,000 barrels of crude oil and 55 million cubic feet of natural gas over the next three months.

Blind Faith Production Startup Delayed
Type: Operator Update

May. 2008 - The company also said production at its Blind Faith project in the deepwaters of the Gulf of Mexico will be delayed until the second half of the year due to a problem with its mooring lines. The project, with an expected yield production capacity of 70,000 barrels a day, was expected to come on line in the second quarter.

Blind Faith Heads Home to Gulf of Mexico
Type: Development Activity

Mar. 2008 - Blind Faith's deep draft semi-submersible is heading for its permanent home, 160 miles southeast of New Orleans in the U.S. Gulf of Mexico. Initial production is expected to be approximately 30,000 barrels of oil and 30 million cubic feet of gas per day. Once it reaches its final destination in the Gulf of Mexico, Blind Faith will be Chevron's deepest offshore producing facility, moored in 6,500 feet of water with production wells in 7,000 feet of water.

Chevron Makes Move with Blind Faith in GOM
Type: Status Update

Feb. 2008 - Blind Faith, the cornerstone of Chevron's $900 Gulf of Mexico project, was moved out of a coastal Texas city over the weekend and is being towed to its deepwater home 160 miles southeast of New Orleans.

Blind Faith Pipelay Completed
Type: Pipeline Construction

Nov. 2007 - Steel catenary riser installed on Blind Faith by Subsea7.

Aker Kvaerner Deepwater Completes Blind Faith Platform
Type: Facility Construction

Sep. 2007 - Aker Kvaerner has successfully completed the semisubmersible hull for Chevron's Blind Faith platform. Before leaving the yard for its final destination, the Blind Faith hull was named Frøya at a traditional naming ceremony at the Aker Kvaerner yard.

Aker Kvaerner Deepwater Completes Blind Faith Platform
Type: Contract Award

Sep. 2007 - Aker Kvaerner has successfully completed the semisubmersible hull for Chevron's Blind Faith platform. The Blind Faith platform was the first use of Aker Kvaerner's deep draft semisubmersible (DDS) concept.

Subsea 7 Prepares for Pipeline Installation
Type: Pipeline Construction

Sep. 2007 - Two x 7km 7in pipelines have been fabricated at Subsea 7's spoolbase in Leith and are currently being spooled onboard the Seven Oceans. The vessel will transit to Theodore, Alabama, US for project equipment mobilization prior to the in-field installation operations that will take place late September/early October 2007.

Aker Kvaerner to Provide Umbilicals for Blind Faith
Type: Contract Award

Feb. 2006 - Aker Kvaerner has been awarded a contract by Chevron to deliver an advanced dynamic umbilical, including engineering and project management, for the Blind Faith deep water development in the Gulf of Mexico.

Mustang Engineering Providing Detailed Design for Blind Faith Project
Type: Contract Award

Jan. 2006 - Mustang Engineering is providing the detailed design package for the Blind Faith field development operated by Chevron. Mustang, having completed the pre-FEED and front-end engineering design (FEED) portion of the project, will design the topsides production facilities.

Gulf Island Fabrication Wins Contract to Build Blind Faith Topsides
Type: Facility Construction

Nov. 2005 - Gulf Island Fabrication has been awarded a contract by Chevron to fabricate the topsides for the Blind Faith platform located in the Gulf of Mexico in approximately 7,000 feet of water.

Aker Kvaerner to Build Blind Faith Hull and Mooring System
Type: Facility Construction

Oct. 2005 - Chevron, with partner Kerr-McGee, has awarded Aker Kvaerner the semisubmersible hull and mooring system contract for their Blind Faith project in the Gulf of Mexico.

Chevron Proceeds with New Deepwater Gulf of Mexico Project
Type: Development Activity

Oct. 2005 - Chevron says that it is proceeding with the development of the Blind Faith Field in the deepwater Gulf of Mexico. The field will be developed using a semisubmersible production facility, with first production expected during the first half of 2008.

ChevronTexaco Assumes Operatorship of Blind Faith Prospect
Type: Acreage Acquisition

Oct. 2003 - ChevronTexaco has reached an agreement to acquire additional working interest and assume operatorship of the Blind Faith discovery from BP. Under the terms of the agreement, ChevronTexaco will earn the right to operate Blind Faith with a 50% WI and BP will own a 50% WI.

BP and Texaco Make New Deepwater Discovery
Type: New Discovery

Jun. 2001 - BP and Texaco announced an oil discovery in approximately 7,000 feet of water on Mississippi Canyon 696. The discovery well was drilled on a prospect called Blind Faith to a total depth exceeding 25,000 feet from the water line.

Blind Faith Semisub
Producing - Nov 2008 to -

Under Construction - Feb 2006 to Nov 2008

Production is expected to start in the 2nd half of 2008.

Blind Faith
Producing - Nov 2008 to -

Under Development - Oct 2005 to Nov 2008

Production start up is expected in the 2nd half of 2008.

Discovery (Appraised) - Apr 2004 to Oct 2005

Appraisal Drilling - Jan 2004 to Apr 2004

The MC696 #2 appraisal well was drilled by the Deepwater Pathfinder. The field has an estimated gross resource potential exceeding 100 million barrels of oil-equivalent.

Discovery (Drilled) - Sep 2001 to Jan 2004

The discovery well encountered more than 200ft of net pay. Appraisal wells to follow.

Exploratory Drilling - Jan 2001 to Sep 2001

The MC696 #1 Blind Faith well was drilled by the Ocean Confidence in 7000' of water and drilled to a depth of over 25,000'.

Bright Spot - Jun 1996 to Jan 2001

Mississippi Canyon 696 acquired in Central Gulf of Mexico Lease Sale 157.

Update History
The SubseaIQ Team works everyday to provide you with the latest information on the offshore field development market. The following table provides you with a detailed record of each addition and update made to this project by the SubseaIQ team.
UPDATE TYPE DATE DAYS AGO
Field Updated Oct 05, 2009 299
Facility Updated Apr 29, 2009 458
Field Updated Mar 11, 2009 507
Activity Added Jan 30, 2009 547
Project Description Added Nov 24, 2008 614
Facility Status Added Nov 13, 2008 625
Field Status Added Nov 13, 2008 625
Activity Added Nov 12, 2008 626
Activity Added May 02, 2008 820
Field Status Added Mar 06, 2008 877
Activity Added Mar 01, 2008 882
Activity Added Feb 26, 2008 886
Activity Added Nov 20, 2007 984
Activity Added Sep 11, 2007 1054
Activity Added Sep 04, 2007 1061
Field Added Sep 03, 2007 1062
Facility Added Sep 03, 2007 1062
Field Status Added Sep 03, 2007 1062
Facility Status Added Sep 03, 2007 1062
Activity Added Feb 23, 2006 1619
Activity Added Jan 10, 2006 1663
Activity Added Nov 04, 2005 1730
Activity Added Oct 19, 2005 1746
Activity Added Oct 10, 2005 1755
Activity Added Oct 30, 2003 2466
Activity Added Jun 21, 2001 3327

    Project Update History Search - View all the lastest updates made by the SubseaIQ team.
 
Project Map
Project Image
Previous Image Next Image
 
 
 
Facility Name Blind Faith Semisub
Duty Oil/Gas
Operator Chevron
Current Status Producing since 2008
Host Type Semisub
Water Depth 1,981 m / 6,537 ft
Dev.Cost $900,000,000
 
Region US
 
Location Mississippi Canyon 696
 
Field Name Blind Faith
Discovery Date Sep 2001
Block Mississippi Canyon 695, 696
Reserve Type Oil/Gas
Current Status Producing
Production Start Nov 2008
Water Depth 2,134 m / 7,042 ft